A stage 1 upgrade of the Crackneck to Cromarty coastal walk at Bateau Bay, carried out for NSW National Parks. An audit of the roughly 1.5 km track identified the priority sections, and we rebuilt two of them: around 224 metres of badly eroded, rutted sandy path, and around 74 metres of track held up by failing block retaining walls.
The old walls were demolished and rebuilt to engineer's specification, mostly as double-course walls with new drainage and footings, using around 180 sandstone blocks of 500 x 500 x 1000 mm. The full length was then finished with a three-layer sealed surface of road base, bitumen emulsion and a 5 to 10 mm pebble topping.
With no road access or power on site, materials were flown in and the old blocks flown out by helicopter, and a 3-tonne excavator was walked in along an old overgrown track cleared with the Parks crew. Because the path was only as wide as the machine, each wall was built working backwards, with blocks placed from tight angles and stone shaped and cut by hand in the bush. An Aboriginal Cultural Heritage Officer inspected the first excavation and attended parts of the demolition, with no finds recorded. Banks were battered to 1:3, coir logs protected the steeper sections, and NSW National Parks revegetated the area once the works were complete, between May and July 2025.
© Copyright Adam's Garden, All Rights Reserved
Made & Hosted by OBSERVED